08/05/08 Pergolas going up on apartments

02/05/08 Terrace and balcony railings go up on many apartments

29/04/08 Main car park starts to take shape

23/04/08 Second floor of Country Club is up

14/04/08 2nd main water tank area prepared

08/04/08 First pavements laid

27/03/08 More top soil going down in gardens

19/03/08 Indoor pool construction taking shape

04/03/08 Prep for top amin water tank underway

19/02/08 Underground pipework begins

06/02/08 Perimeter fencing starts

23/01/08 Steps to main pool area built

10/01/08 Main pool ara dug out

15/12/07 Stone and paint work completed on A1-A5, B1, B5, B6

15/12/07 Windows and Doors being fitted to A1 block

11/12/07 Garden walls and top soil going in around A blocks

11/12/07 Drainage work being installed

11/12/07 Swimming Pools being dug out

11/12/07 Windows being fitted to last of the A Blocks

06/08/07 External stone work in place on A2

17/07/07 Foundations completed in B4 and C9

17/07/07 External stone work in place on B5

17/07/07 A6 and C1 Brick work started

17/07/07 A1 Plastered inside Rendered outside

17/07/07 A2 and A3 Plastered inside and out

30/06/07 Brickwork complete on A1 A2 A3

30/06/07 Brick work continues on A4 A5 B1 and B2

30/06/07 B5 Rendered outside and plastered internally

24/05/07 All founations completed

21/05/07 Brickwork begins in A1

14/05/07 All block foundations almost complete

02 05 07 A1 concrete shell completes

26 04 07 foundations completed in C4

23/04/07 B5 stairs in place

19/04/07 several A blocks at first floor level

16/04/07 foundations completed in B6,B7 and C11

11/04/07 build progress speeds on in B5 in preparation for show flat

07/04/07 foundations completed in B3 and C2

04/04/07 foundations completed in C1 and C3

30/03/07 foundations completed in A2, A5 and B2

25/03/07 foundations completed in A6, B1 and B5

23/03/07 Temporary nursery created for olive trees

20/03/07 foundations completed in A4

16/03/07 foundations completed in A3

15/03/07 foundations completed in A1

12/03/07 Reserve olive trees relocated within Reserve, Marina and Esentepe

08/03/07 Road widened to complex

05/03/07 Foundations begin in A blocks

01/03/07 Building Begins! Ground broken on Reserve site